PROJECT TITLE: Navoi Thermal Power Station Modernization Project (Phase 2) - Survey for LARAP
CLIENT: JICA / TEPSCO
PERIOD: February – October 2019
PROJECT AIM: Abbreviated Land Acquisition and Resettlement Action Plan (A-LARAP) were required to be prepared for the thermal power station and transmission line, according to JICA Guidelines for Environment and Social Consideration.
DESCRIPTION OF ACTUAL SERVICES PROVIDED IN THE ASSIGNMENT:
JICA Survey Team conducted Preparatory Survey on Navoi Thermal Power Station Modernization Project (Phase 2) in the Republic of Uzbekistan. For this project (Including development of transmission line), the need for land acquisition, resettlement and compensation to the land owners occurred. Therefore, Abbreviated Land Acquisition and Resettlement Action Plan (A-LARAP) were required to be prepared for the thermal power station and transmission line, according to JICA Guidelines for Environment and Social Consideration. Collection of basic data of social environment and preparation of A-LARAP report for JICA. Conduct of survey, mainly targeting Thermal Power Plant (Plan B) and area for ROW of transmission line by collecting data and preparing A-LARAP.
1.Survey Implementation
2.Examination of Resettlement Measures and Livelihood Restoration Activities
3.Estimate Costs and Budgets
A-LARAP was prepared in line with requirement of laws and regulations in Uzbekistan and World Bank “Operational Policy 4.10 Annex A Resettlement Plan” and World Bank “Involuntary Resettlement Source Book Planning and Implementation in Development Projects” according to JICA Guidelines for Environment and Social Consideration.